A, B and C can do a piece of work individually in 8, 12 and 15 days respectively. A and B start working together but A quits after working for 2 days. After this, C joins and works till completion of the work. In how many days will the work be completed?
Mathematics
2014
CDS Elementary Mathematics 2014
CDS 2014